Beschrijving:
MAVA project: broadening the A15
Customer: Rijkswaterstaat
Sector: civil engineering
Duration: 2011-2015
The A15 between the Maasvlakte and the Vaanplein has been altered to improve traffic flow and optimise safety. During the MAVA project, a total of 85 km carriageway was added and a new, wider Botlek Bridge was built. We are still involved in asset management for this organisation.
MAVA project goal
The project MAVA Reconstruction A15 Maasvlakte Vaanplein was an assignment by the A-lanes consortium.
Our professionals
For this project, we provided: contract manager document controller head drawing office system engineer constructor quality advisor process planner
Progress
Within this project, we have provided professionals in several disciplines. We are still involved in asset management, increasing our knowledge.